 |
Q. How many chutes do I
need..
A. Generally a 600 dia. chute will serve 40+ apartments.
Refuse chutes should not be more than 30m horizontally from the apartment it
serves. |
 |
Q. What is the life
expectancy for a chute.
A. 25-30 years. |
 |
Q. What is the main
advantage of a steel chute compared to a concrete chute.
A. Steel chute sections are relatively light weight and can
be man handled into position. Typically a 10 storey chute can be installed in 3 to 4
days as soon as the building structure is complete and the roof is in place. Concrete
chute are heavy, cumbersome and need to be installed at stages using a crane for lifting
in to place. |
 |
Q. Can a refuse chute be
located on a stair landing.
A. Refuse chutes in any new building
have to satisfy the Building Regulations, approved document B1, Clause5.48 'Refuse
chutes and rooms provided for the storage of refuse should: a. be separated from other
parts of the building by fire-resisting construction, and b. not be located within
protected stairways or protected lobbies'. |
 |
Q. Do Hardall refuse
chutes need additional sound proofing.
A. We always recommend coating the chute in 'Revac DC1010'
sound deadening compound. (For product information page click
here >). If the chute is to be located adjacent habitable
rooms then additional sound proofing may be required in order
to satisfy the requirements of Building Regulations approved document E, section 1, clause
1.3 'A wall separating a habitable room or kitchen and a refuse chute
should have a mass of at least 1320kg/m2. A wall separating a non habital
room, which is in a dwelling, from a refuse chute should have a mass of at least 220kg/m2.
Hardall chutes are supported by a special clampband which incorporates a 3mm rubber insert
to isolate the chute from the structure. This combined with the Revac sound
deadening compound and a separating wall of dense concrete blockwork and/or a cavity wall
construction will normally satisfy building control. As an alternative to Revac,
Hardall can wrap the chute in a high density 'Punf' foam & barrier matt for additional
sound proofing. |
 |
Q. How high can a single
chute go.
A. 40 storeys is about the maximum. |
 |
Q. Does the chute require
any baffles to slow down the fall of refuse.
A. Baffles are not part of Hardalls chute design. |
 |
Q. Can a refuse chute be
offset to avoid structural obstacles or change direction.
A. Yes, but the angle of inclination of the offset section
must not be less than 45º from the horizontal, 70º is recommended. |
 |
Q. Is the chute fire
rated.
A. The chute its self does not have any certified fire
resistance, but the combination of fire rated hopper doors, an automatic fire door and
enclosing walls create a fire protected chute system. |
 |
Q. Do the floors around
the chute need fire-stopping.
A. Only the bottom floor at fire door level, enclosing
walls around the chute then form a fire protected shaft. |
 |
Q. Can the vent pipe
terminate inside a vented roof space.
A. This would be acceptable for a linen chute, but a refuse
chute must be vented to atmosphere. |
 |
Q. Do I have to have a
separate vented lobby accessing the chute.
A. Yes, to comply with UK Building Regulations 2000,
approved document B1, 'means of warning and escape'. clause 6.52.'Rooms
containing refuse chutes, should be approached either directly from the open air or by way
of a protected lobby provided with not less than 0.2m2 of permanent
ventilation.' |
 |
Q. Does the automatic fire
door need a power supply.
A. No, it is mechanical and operates on breakage of a 70ºC
fusible link. |
 |
Q. Can the fire door be
linked in to the building fire alarm system.
A. Yes, either it can activate an alarm
via a simple limit switch, or if fitted with electro-magnets the fire door can actually be
triggered by a fire alarm. This is treated as an optional extra and not part of the
standard fire door design. |
 |
Q. What are the minimum
enclosure dimensions for a 600dia refuse chute.
A. 350mm centre to back wall, 690mm centre to front face
and 800mm wide (For illustration page click
here >). |
 |
Q. How is the floor around
the chute made good.
A. It is quite acceptable to just
shutter up and concrete the floor around the chute, although this normally only needs
doing at the bottom floor level immediately above the fire door. |
 |
Q. Do you survey before
commencing manufacture.
A. Manufacture will commence on
approval of shop drawings or if the program dictates. A site survey will be carried
out, normally 1-2 weeks prior to installation. |
 |
Q. What maintenance is
required.
A. Generally a basic chute should require very little
maintenance. However if a chute cleaning system and interlocks are included then we
will recommend a preventative maintenance contract. In
addition a chute cleaning service, utilising high pressure jet washing is available.
|